Follow-up report to the 2019-20 procurement practice review of the Department of Fisheries and Oceans Canada
June 2023
On this page
Introduction
1. As a standard practice, the Office of the Procurement Ombudsman (OPO) follows up on the recommendations made in Procurement Practice Reviews (PPRs) approximately two years after those recommendations are published.
2. Follow-up reviews allow OPO to provide assurance that actions to respond to PPR recommendations have been effectively implemented, or that senior management has accepted the risk of not taking action; and provide an organizational report card that facilitates comparisons across federal organizations over time.
3. In 2019-2020 OPO conducted a PPR entitled Procurement practice review of the Department of Fisheries and Oceans Canada (DFO). The final report was issued in February 2020.
4. The initial review was undertaken to determine whether DFO’s procurement practices pertaining to evaluation criteria and selection plans, solicitation, and evaluation of bids and contract award, supported the principles of fairness, openness and transparency. To make this determination, OPO examined whether DFO’s procurement practices were consistent with Canada’s obligations under applicable sections of national and international trade agreements, the Financial Administration Act and regulations made under it, the Treasury Board Contracting Policy and, when present, departmental guidelines.
5. The following three lines of inquiry (LOE) were used to assess the highest-risk procurement elements:
- LOE 1: Evaluation criteria and selection plans were established in accordance with applicable laws, regulations and policies
- LOE 2: Solicitation documents and organizational practices during the bid solicitation period were consistent with applicable laws, regulations and policies
- LOE 3: Evaluation of bids and contract award were conducted in accordance with the solicitation
6. Regarding LOE 1, which reviewed evaluation criteria and selection plans, OPO’s initial review found issues with half of the applicable procurement files. In two cases (i.e., lowering the security requirement, and obtaining a quote from one supplier before posting the solicitation), one bidder was favoured over others. In the other cases, either the criteria themselves or the selection methodology were unclear or contained discrepancies. These issues were noted as potentially leading to non-compliant bids and improper evaluations, thus impacting the fairness of the procurement process.
7. Regarding LOE 2, which reviewed solicitation documents and DFO’s actions during the solicitation process, OPO found issues with a third of the applicable procurement files, including one case where DFO purposely modified the requirement to remain within the ProServices method of supply and below the Task and Solutions professional services (TSPS) threshold. In 6 cases, DFO appeared to favour one bidder over others or found ways to limit the bidder pool, thereby affecting the openness of those procurements. In 4 other cases (one where the rotation/ proportion was unclear and 3 where DFO did not provide correct information during the solicitation process), the transparency and fairness of the processes were negatively impacted by DFO’s actions.
8. Regarding LOE 3, which reviewed the evaluation of bids and contract award, OPO found issues with 4 of 24 applicable procurement files. Overall, DFO properly informed its evaluators of how to conduct those processes. DFO also sought to ensure that potential conflict of interest could be mitigated by requiring one of the evaluators to be outside the span of control of the project authority. This positive step is significant because this stage of procurement has the greatest potential to affect the overall competitive process given its importance vis-à-vis awarding the contract to the correct bidder in a fair, open and transparent manner. Of concern were 2 cases where the evaluators appeared to be in a potential conflict position, including a case where the evaluation of the lower-priced bid, and the individual evaluations of the winning bid, were missing.
9. In order to address the issues identified during the initial review, the Procurement Ombudsman made 6 recommendations: 3 recommendations under LOE 1, 1 recommendation under LOE 2, and 2 recommendations under LOE 3.
Methodology
10. In May 2022, OPO asked DFO to self-assess their progress in implementing the 6 recommendations using an established progress scale, ranging from “no progress” (level 1) to “full implementation” (level 5), as outlined in Appendix 1. DFO was also asked to provide supplementary information and documentation to explain and support their self-assessment.
11. When reviewing departments’ self-assessments during a follow-up exercise, OPO may conduct additional testing of procurement files, if required, to obtain evidence that demonstrates structures and processes have been implemented and positive results have been identified. During this review, it was determined that additional testing of procurement files was not necessary because DFO’s self-assessment and supporting documentation provided sufficient evidence regarding the actions taken to resolve the issues noted in the initial review.
12. OPO reviewed and assessed the information provided by DFO in its self-assessment for its overall reasonableness and credibility. This report also includes a summary, a report card, and an overall conclusion regarding progress made by DFO in implementing the recommendations made by the Procurement Ombudsman in the initial report.
Management Action Plan Assessment—Summary
13. Using the scale provided by OPO, DFO self-assessed the level of implementation of its actions at a level 5, i.e. “Full Implementation”, for all 6 recommendations in the initial PPR report. However, substantiating documentation provided by DFO did not clearly demonstrate structures and processes being fully implemented for 5 of the 6 recommendations. Therefore, OPO is not in full agreement with DFO’s self-assessment, and assessed DFO’s level of implementation at level 4 (“Substantial implementation”) for 5 of the 6 recommendations.
14. Overall, DFO developed and implemented both new and enhanced products that support fairness, openness, and transparency in the procurement process. The evidence provided by DFO demonstrated a series of advancements designed to meet the intent of each recommendation through a series of initiatives, including: new guides and information resources; updated training programs and checklist tools; a new, standardized electronic file retention methodology through the GCdocs platform; new standardized templates with instructions on how to complete them; and a new oversight guidance tool to assist with quality control and oversight. Best practices such as formal lessons-learned meetings, onboarding programs for new procurement staff and assigning dedicated teams to different client sectors were adopted. DFO has also established a formal Contract Review Committee and is participating in an ongoing procurement streamlining initiative. Some initiatives such as the Contracting Planning and Approval document cover multiple recommendations. Despite these positive advancements, there is an opportunity for DFO to adopt better documentation practices around some of their initiatives and practices. Additional details of OPO’s overall assessment of DFO’s response to each recommendation are included in Appendix 3.
Report Card
15. PPR follow-up reviews include a report card with a rating that depicts the organization’s performance with regard to the 3 LOEs, resulting in 3 assessments. In determining these assessment ratings, OPO takes into consideration the results from the initial PPR, and the actions taken by the organization to implement the PPR recommendations under each LOE. The assessment ratings are as follows:
- Satisfactory +
- Satisfactory
- Partially Satisfactory
- Unsatisfactory
16. Note that a Satisfactory + assessment rating is only possible when the initial PPR resulted in no recommendations being issued under a particular LOE. As the initial PPR report contained recommendations under all 3 LOEs, a Satisfactory + rating was not possible in this follow-up review, and the highest possible score DFO could obtain for each LOE was Satisfactory. Assessment definitions and criteria are outlined in Appendix 2.
17. After a review of progress made toward implementing the action plans for each recommendation, and in consideration of the established assessment ratings, a rating of Satisfactory is awarded for each LOE. DFO’s descriptions of actions taken, and the supporting documentation provided demonstrate reasonable and credible progress has been achieved in response to all recommendations, although more formal documentation would serve to strengthen DFO’s efforts and help it to be better prepared for the scrutiny of future internal audit activity and to defend against external challenges.
Line of Inquiry (LOE) | Rating | Assessment |
---|---|---|
1. Evaluation criteria and selection plans were established in accordance with applicable laws, regulations and policies. | Satisfactory |
|
2. Solicitation documents and organizational practices during the bid solicitation period were consistent with applicable laws, regulations and policies. | Satisfactory |
|
3. Evaluation of bids and contract award were conducted in accordance with the solicitation. | Satisfactory |
|
DFO’s overall report card rating is “Satisfactory”. The key factors contributing to this rating include:
- Initial PPR resulted in one or more recommendations under each of the three LOEs, therefore the highest possible score DFO could obtain for each LOE was Satisfactory;
- Action plan(s) have achieved level 5 implementation or a combination of level 4 and level 5 that is deemed to be satisfactory, i.e., significant progress has been made to implement action plan(s) that address recommendation(s).
- DFO's response is supported with some documentation, but work remains to be done with respect to documentation supporting DFO’s oversight function.
Conclusion
18. DFO has implemented new initiatives and enhanced established products that support fairness, openness, and transparency in the procurement process. The evidence provided demonstrates a series of advancements designed to meet the intent of each recommendation through a series of best practice initiatives. These initiatives included development of internal policy instruments such as guides and directives, updated training programs, new manual and automated tools and development of a procurement oversight process, specifically involving a Contract Review Committee that reviews the Departmental Procurement Plan to ensure compliance with policy frameworks and transparency in planning. There is an opportunity for DFO to further develop clear internal policy, procedures and/or guidance documentation that demonstrates support of a formal peer review function and its communication to responsible staff, to fully implement all recommendations stemming from the initial PPR.
Appendix 1
Level | Assessment |
---|---|
Level 1 | No progress or insignificant progress. Actions such as establishing a new committee, conducting meetings, and generating informal plans have not advanced, or insignificant progress has been made. |
Level 2 | Planning stage. Formal plans for organizational changes have been created and approved. |
Level 3 | Preparations for implementation. Preparations for implementing a recommendation are in progress—for example, hiring or training staff, developing necessary resources, drafting and adopting policy documents, etc. |
Level 4 | Substantial implementation. Structures and processes are in place and integrated within at least most parts of the organization, and some achieved results have been identified. |
Level 5 | Full implementation. Structures and processes are fully implemented, and positive results have been identified. |
Obsolete | Recommendation is no longer applicable due to new policies, procedures, etc. |
Appendix 2
Overall performance | Assessment |
---|---|
Satisfactory + |
|
Satisfactory |
|
Partially satisfactory |
|
Unsatisfactory |
|
Appendix 3
Number | Recommendation | OPO Assessment | Rating |
---|---|---|---|
1 | DFO should ensure all procurement records are retained, organized and accessible, for the period of time required by Treasury Board record-keeping standards. | DFO has substantially implemented this recommendation through:
|
Level 4 Substantial Implementation |
2 | DFO should ensure evaluation criteria are reviewed to eliminate bias and ensure clarity prior to publication. | DFO has substantially implemented the recommendation through adoption of training and client engagement initiatives. Together, these activities help meet the intent of the recommendation by helping employees better understand criteria requirements and how they fit into the overall evaluation process, as well as how to recognize bias and take steps to mitigate the risk of it impacting evaluation results. DFO has done this through:
DFO referred to the Contracting Planning and Approval document as their established evaluation process that helps ensure proposed evaluation criteria are aligned with potential procurement instruments. However, there is a lack of clear linkage that demonstrates how exactly it ensures proposed evaluation criteria are aligned with potential procurement instruments. DFO would benefit from reviewing the CPAA to provide an indication as to how assurance is demonstrated that evaluation criteria are reviewed to eliminate bias and ensure clarity prior to publication. Iterating on the document to clearly highlight how it is used to ensure evaluation criteria are reviewed to eliminate bias and ensure clarity prior to publication would help to fully implement the recommendation. |
Level 4 Substantial Implementation |
3 | DFO should ensure clarity and consistency in its solicitation documents to avoid discrepancies and ensure transparency in its bidding processes. | DFO has substantially implemented the recommendation through adherence to guidance documentation, active monitoring and oversight and information sharing among employees. These activities serve to meet these goals in a variety of ways:
|
Level 4 Substantial Implementation |
4 | DFO should properly document its files to demonstrate how its contracting personnel are giving all qualified firms an equal opportunity for access to government business, and how its contracting personnel are decreasing any possible bias or incumbent advantage. | DFO has substantially implemented the recommendation through:
|
Level 4 Substantial Implementation |
5 | DFO should ensure that a standard “evaluation package” including a Confidentiality form and Conflict of Interest form are signed by all evaluators and recorded on file prior to providing evaluators access to bids. | DFO has fully implemented their action plan to address this recommendation. Their activities include:
|
Level 5 Full Implementation |
6 | DFO should put a mechanism in place to ensure evaluation processes are adhered to and contracts are awarded to the appropriate, qualified bidder. | DFO has substantially implemented the recommendation through use of formal oversight bodies, peer review and a procurement streamlining initiative. These activities help ensure evaluation processes are adhered to and that contracts are awarded to the appropriate bidder by providing formal monitoring, oversight and direction to employees to ensure processes are followed throughout the span of the engagement. For example:
|
Level 4 Substantial Implementation |
- Date modified: